27INR0385 · Solar · Andrews County
Straight Spur Solar
Straight Spur Solar is a 252 MW solar project in Andrews County, Texas, connecting at Tap 345 kV ClearFork (Bus #23876) to Gardenale Switch (Bus #11157). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0385
- Capacity
- 252 MW
- Fuel
- Solar (PV)
- County
- Andrews County
- Interconnecting entity
- ENGIE IR Holdings LLC
- Projected COD
- 04/01/2029
- Entered queue
- 11/08/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/08/2024Entered the queue with 252 MW, projected COD 04/01/2029
- 11/08/2024Screening → FIS Requested