ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0384 · Wind · Andrews County

Straight Spur Wind

Straight Spur Wind is a 247 MW wind project in Andrews County, Texas, connecting at Tap 345 kV 23876 Clear Fork -11157 Gardenale Switch. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0384
Capacity
247 MW
Fuel
Wind (WT)
Interconnecting entity
ENGIE IR Holdings LLC
Projected COD
04/01/2029
Entered queue
12/06/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/06/2024
    Entered the queue with 247 MW, projected COD 04/01/2029
  • 12/06/2024
    Screening → FIS Requested