27INR0315 · BESS · Reagan County
Old Roman Energy Center
Old Roman Energy Center is a 207 MW battery storage project in Reagan County, Texas, connecting at 23868 STILES 138 KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/26/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0315
- Capacity
- 207 MW
- Fuel
- BESS (BA)
- Substation
- 23868 STILES 138 KV
- County
- Reagan County
- Interconnecting entity
- Nova Clean Energy LLC
- Projected COD
- 07/26/2029
- Entered queue
- 08/30/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/30/2024Entered the queue with 207 MW, projected COD 07/26/2029
- 08/30/2024Screening → FIS Requested