27INR0274 · BESS · Zavala County
Flying Kite Bess
Flying Kite Bess is a 105 MW battery storage project in Zavala County, Texas, connecting at Tap the 138 kV La Pryor (#8008) - Poblano (#8009). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/30/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0274
- Capacity
- 105 MW
- Fuel
- BESS (BA)
- County
- Zavala County
- Interconnecting entity
- Flying Kite BESS, LLC
- Projected COD
- 12/30/2027
- Entered queue
- 07/22/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/22/2024Entered the queue with 105 MW, projected COD 12/30/2027
- 07/22/2024Screening → FIS Requested
Other projects at this substation
| Flying Kite Solar | Solar | 80 MW | IA Signed |