27INR0252 · BESS · Austin County
Parula Energy Center
COD delayed 1×
Parula Energy Center is a 251 MW battery storage project in Austin County, Texas, connecting at 7287 Bellville North 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/18/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0252
- Capacity
- 251 MW
- Fuel
- BESS (BA)
- Substation
- 7287 Bellville North 138kV
- County
- Austin County
- Interconnecting entity
- Parula Energy Center
- Projected COD
- 06/18/2029
- Entered queue
- 05/09/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/30/2027 → 06/18/2029 (+21 months)
- 05/09/2024Entered the queue with 251 MW, projected COD 09/30/2027
- 05/09/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.