ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0231 · BESS · Schleicher County

Easy Battery Energy Storage Center

Easy Battery Energy Storage Center is a 200 MW battery storage project in Schleicher County, Texas, connecting at Tap 345 kV 76003 Big Hill to 76005 Schneeman Draw. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0231
Capacity
200 MW
Fuel
BESS (BA)
Interconnecting entity
Easy Wind Energy Center, LLC
Projected COD
06/15/2029
Entered queue
03/20/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/20/2024
    Entered the queue with 200 MW, projected COD 06/15/2029
  • 03/20/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.