27INR0217 · Solar · Haskell County
Journey Solar
Journey Solar is a 125 MW solar project in Haskell County, Texas, connecting at Tap 138kV Paint Creek 6161 - Aspermont 6158. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/14/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0217
- Capacity
- 125 MW
- Fuel
- Solar (PV)
- County
- Haskell County
- Interconnecting entity
- Journey Solar, LLC
- Projected COD
- 09/14/2027
- Entered queue
- 03/14/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/14/2024Entered the queue with 125 MW, projected COD 09/14/2027
- 03/14/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.