27INR0180 · BESS · Bexar County
Otter BESS
Otter BESS is a 157 MW battery storage project in Bexar County, Texas, connecting at 5378 SHEPHERD RD 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0180
- Capacity
- 157 MW
- Fuel
- BESS (BA)
- Substation
- 5378 SHEPHERD RD 138kV
- County
- Bexar County
- Interconnecting entity
- GRS BESS TEXAS TEN, LLC
- Projected COD
- 09/15/2029
- Entered queue
- 02/05/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/05/2024Entered the queue with 157 MW, projected COD 09/15/2029
- 02/05/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.