ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0169 · Solar · Victoria County

Marcos Solar SLF

Marcos Solar SLF is a 216 MW solar project in Victoria County, Texas, connecting at To the 138 kV line from EDNA (#8118) to VICTORIA4A (#8172). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 08/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0169
Capacity
216 MW
Fuel
Solar (PV)
Interconnecting entity
GRS BESS Texas Eight
Projected COD
08/15/2028
Entered queue
12/28/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/28/2023
    Entered the queue with 216 MW, projected COD 08/15/2028
  • 12/28/2023
    Screening → FIS Requested

Other projects at this substation

Marcos BESSBESS116 MWFIS Requested