27INR0146 · Solar · Pecos County
Larrea Solar
COD delayed 1×
Larrea Solar is a 232 MW solar project in Pecos County, Texas, connecting at Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/18/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0146
- Capacity
- 232 MW
- Fuel
- Solar (PV)
- County
- Pecos County
- Interconnecting entity
- Greasewood IV LLC
- Projected COD
- 09/18/2029
- Entered queue
- 01/03/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/18/2027 → 09/18/2029 (+24 months)
- 06/05/2024Screening → FIS Requested
- 01/03/2024Entered the queue with 232 MW, projected COD 09/18/2027