27INR0143 · BESS · Castro County

Ogalalla Storage

Ogalalla Storage is a 252 MW battery storage project in Castro County, Texas, connecting at 23912 OGALLALA_5 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/15/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0143
Capacity
252 MW
Fuel
BESS (BA)
Interconnecting entity
Hecate Energy Ogalalla Solar LLC
Projected COD
04/15/2028
Entered queue
01/03/2024
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/19/2024
    Screening → FIS Requested
  • 01/03/2024
    Entered the queue with 252 MW, projected COD 04/15/2028

Other projects at this substation

No other projects at this substation.