27INR0127 · Solar · King County
Bigway Solar I
Bigway Solar I is a 195 MW solar project in King County, Texas, connecting at Tap 345kV 59904 Cottonwood - 60500 Edith Clarke Ckt #2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0127
- Capacity
- 195 MW
- Fuel
- Solar (PV)
- County
- King County
- Interconnecting entity
- NextEra Energy Interconnection Holdings, LLC
- Projected COD
- 12/31/2027
- Entered queue
- 01/11/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/15/2025FIS Requested → IA Signed
- 02/28/2024Screening → FIS Requested
- 01/11/2024Entered the queue with 195 MW, projected COD 12/31/2027
Other projects at this substation
| Bigway Solar II | Solar | 206 MW | IA Signed |