LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0118 · Solar · Hidalgo County

Grapefruit Solar

Withdrawn

Grapefruit Solar is a 291 MW solar project in Hidalgo County, Texas, connecting at North Edinburg (Bus #8905) - Reforzar (Bus # 80078) 345kV. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0118
Capacity
291 MW
Fuel
Solar (PV)
Interconnecting entity
Grapefruit Solar LLC
Projected COD
12/31/2028
Entered queue
01/26/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/30/2026
    Listed as inactive
  • 08/31/2026
    FIS Requested → FIS Approved
  • 04/10/2025
    FIS Approved → IA Signed
  • 01/26/2024
    Entered the queue with 291 MW, projected COD 12/31/2028
  • 01/26/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.