ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0109 · BESS · Montgomery County

Two Barbaras BESS

Two Barbaras BESS is a 217 MW battery storage project in Montgomery County, Texas, connecting at Tap 138 kV Pinehurst (#46240) – Mill Creek (#44850) Line. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/04/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0109
Capacity
217 MW
Fuel
BESS (BA)
Interconnecting entity
Two Barbaras BESS
Projected COD
01/04/2029
Entered queue
03/14/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2025
    FIS Requested → IA Signed
  • 03/14/2024
    Entered the queue with 217 MW, projected COD 01/04/2029
  • 03/14/2024
    Screening → FIS Requested