27INR0102 · BESS · Wharton County

Cottonseed Energy Storage

Cottonseed Energy Storage is a 208 MW battery storage project in Wharton County, Texas, connecting at South Lane City and PSEE # is 43190. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/20/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0102
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
Cottonseed Energy Storage LLC
Projected COD
04/20/2027
Entered queue
11/02/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/23/2024
    FIS Requested → FIS Approved
  • 11/02/2023
    Entered the queue with 208 MW, projected COD 04/20/2027
  • 11/02/2023
    Screening → FIS Requested