27INR0091 · BESS · Lavaca County
Oak Tree Energy Storage
Oak Tree Energy Storage is a 310 MW battery storage project in Lavaca County, Texas, connecting at Tap Shaula (#5380) – South Texas (#5915). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/20/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0091
- Capacity
- 310 MW
- Fuel
- BESS (BA)
- Substation
- Tap Shaula (#5380) – South Texas (#5915)
- County
- Lavaca County
- Interconnecting entity
- Live Oak Energy Storage, LLC
- Projected COD
- 09/20/2030
- Entered queue
- 11/21/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/26/2026FIS Requested → IA Signed
- 11/21/2023Entered the queue with 310 MW, projected COD 09/20/2030
- 11/21/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.