ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0047 · Solar · Nueces County

Sunscape Renewable Energy Solar SLF

Sunscape Renewable Energy Solar SLF is a 523 MW solar project in Nueces County, Texas, connecting at Bus# 8455 Lon C Hill to Bus# 80078 Reforzar 345 kV Line. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0047
Capacity
523 MW
Fuel
Solar (PV)
Interconnecting entity
Sunscape Renewable Energy LLC
Projected COD
10/31/2028
Entered queue
05/30/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/18/2024
    FIS Requested → IA Signed
  • 05/30/2023
    Entered the queue with 523 MW, projected COD 10/31/2028
  • 05/30/2023
    Screening → FIS Requested

Other projects at this substation