LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0774 · BESS · Austin County

Wallis BESS2

Wallis BESS2 is a 9.9 MW battery storage project in Austin County, Texas, connecting at Wallis. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/22/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0774
Capacity
9.9 MW
Fuel
BESS (BA)
Substation
Wallis
Interconnecting entity
Denali Energy Storage LLC
Projected COD
02/22/2027
Entered queue
12/11/2024
ERCOT zone
SOUTH
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/11/2024
    Entered the queue with 9.9 MW, projected COD 02/22/2027
  • 12/11/2024
    Screening → IA Signed

Other projects at this substation

No other projects at this substation.