LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0714 · BESS · Matagorda County

Pavlov BESS2

COD delayed 1×

Pavlov BESS2 is a 10 MW battery storage project in Matagorda County, Texas, connecting at New DESR on the coordinates above tie at 12.47kV to: TSP Station Name: Pavlov TSP Station Code: PAVLOV Load Name: 138_13_1 Bus #: PTI Bus Number: 8608 Voltage (Transmission level kV): 138kV Node (load/load XFMR in NMMS), Tranformer: LD01. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/13/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0714
Capacity
10 MW
Fuel
BESS (BA)
Interconnecting entity
Matagorda Clean Energy Center, LLC
Projected COD
12/13/2026
Entered queue
06/18/2025
ERCOT zone
COASTAL
Size category
Small

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 08/29/2026 → 12/13/2026 (+3 months)
  • 06/18/2025
    Entered the queue with 10 MW, projected COD 08/29/2026
  • 06/18/2025
    Screening → IA Signed