26INR0654 · BESS · Atascosa County
Great Hambino BESS
COD delayed 1×
Great Hambino BESS is a 123 MW battery storage project in Atascosa County, Texas, connecting at #5700 Miracle Lake Substation 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0654
- Capacity
- 123 MW
- Fuel
- BESS (BA)
- Substation
- #5700 Miracle Lake Substation 138kV
- County
- Atascosa County
- Interconnecting entity
- Atascosa BESS, LLC
- Projected COD
- 10/01/2028
- Entered queue
- 09/10/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2027 → 10/01/2028 (+12 months)
- 09/10/2025Entered the queue with 123 MW, projected COD 10/01/2027
- 09/10/2025Screening → FIS Requested
Other projects at this substation