26INR0614 · BESS · Bell County
Bell County Leifester Storage
Bell County Leifester Storage is a 205 MW battery storage project in Bell County, Texas, connecting at Tap 138kV 3428 Killeen South – 13628 Founders Trail Sub. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/17/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0614
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- County
- Bell County
- Interconnecting entity
- DM-BCRCML, LLC
- Projected COD
- 09/17/2029
- Entered queue
- 11/14/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/14/2024Entered the queue with 205 MW, projected COD 09/17/2029
- 11/14/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.