26INR0574 · BESS · Ector County
Apple BESS
COD delayed 1×
Apple BESS is a 9.9 MW battery storage project in Ector County, Texas, connecting at Apple. ERCOT's October 2026 report shows it at the Energization Approved stage with a projected commercial operation date of 11/27/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0574
- Capacity
- 9.9 MW
- Fuel
- BESS (BA)
- Substation
- Apple
- County
- Ector County
- Interconnecting entity
- Apple Infra LLC
- Projected COD
- 11/27/2026
- Entered queue
- 04/03/2025
- ERCOT zone
- WEST
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/05/2026 → 11/27/2026 (+2 months)
- 08/04/2026IA Signed → Energization Approved
- 04/03/2025Entered the queue with 9.9 MW, projected COD 10/05/2026
- 04/03/2025Screening → IA Signed