26INR0551 · BESS · Brazoria County

Hastings Park BESS

COD delayed 1×

Hastings Park BESS is a 256 MW battery storage project in Brazoria County, Texas, connecting at 39010 138kV HASTINGS. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/27/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0551
Capacity
256 MW
Fuel
BESS (BA)
Interconnecting entity
Brazos Roots BESS, LLC
Projected COD
02/27/2028
Entered queue
08/09/2024
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/15/2027 → 02/27/2028 (+5 months)
  • 08/13/2025
    FIS Approved → IA Signed
  • 03/21/2025
    FIS Requested → FIS Approved
  • 08/09/2024
    Entered the queue with 256 MW, projected COD 09/15/2027
  • 08/09/2024
    Screening → FIS Requested

Other projects at this substation