26INR0543 · Solar · Navarro County

Three Canes Solar

Withdrawn

Three Canes Solar is a 334 MW solar project in Navarro County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0543
Capacity
334 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
08/03/2026
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/03/2026
    Listed as inactive

Other projects at this substation