LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0525 · BESS · Fort Bend County

Bypass BESS II

Bypass BESS II is a 206 MW battery storage project in Fort Bend County, Texas, connecting at 44000 Wa Parish 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0525
Capacity
206 MW
Fuel
BESS (BA)
Interconnecting entity
Bypass BESS II LLC
Projected COD
04/30/2028
Entered queue
10/23/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/23/2024
    Entered the queue with 206 MW, projected COD 04/30/2028
  • 10/23/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.