26INR0505 · BESS · Victoria County
Goldhill Energy Storage
Goldhill Energy Storage is a 201 MW battery storage project in Victoria County, Texas, connecting at Tap 138kV 8154 VISTRON4B – 8189 TUNGSTEN4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0505
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Victoria County
- Interconnecting entity
- Goldhill Energy Storage LLC
- Projected COD
- 09/30/2028
- Entered queue
- 04/15/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/15/2024Entered the queue with 201 MW, projected COD 09/30/2028
- 04/15/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.