26INR0503 · BESS · Harris County

Rex Storage

COD delayed 1×

Rex Storage is a 256 MW battery storage project in Harris County, Texas, connecting at Tap 138 kV 48096 El Dorado - 43610 Scarsdale CKT 92. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/30/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0503
Capacity
256 MW
Fuel
BESS (BA)
Interconnecting entity
Rex BESS, LLC
Projected COD
10/30/2028
Entered queue
06/04/2024
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/15/2027 → 10/30/2028 (+14 months)
  • 06/04/2024
    Entered the queue with 256 MW, projected COD 09/15/2027
  • 06/04/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.