26INR0466 · BESS · Austin County
Symphony BESS
Symphony BESS is a 612 MW battery storage project in Austin County, Texas, connecting at 46220 PETERS. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0466
- Capacity
- 612 MW
- Fuel
- BESS (BA)
- Substation
- 46220 PETERS
- County
- Austin County
- Interconnecting entity
- Symphony BESS, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 01/28/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/28/2025Entered the queue with 612 MW, projected COD 07/01/2028
- 01/28/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.