LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0453 · BESS · Glasscock County

Cannibal Draw Storage

Cannibal Draw Storage is a 99 MW battery storage project in Glasscock County, Texas, connecting at Sand_Bluff 345 kV (59902). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/10/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0453
Capacity
99 MW
Fuel
BESS (BA)
Interconnecting entity
Cannibal Draw Solar, LLC
Projected COD
04/10/2028
Entered queue
06/10/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/17/2025
    FIS Requested → IA Signed
  • 06/10/2024
    Entered the queue with 99 MW, projected COD 04/10/2028
  • 06/10/2024
    Screening → FIS Requested

Other projects at this substation

Cannibal Draw SolarSolar150 MWIA Signed