Sullivan Solar is a 171 MW solar project in Hidalgo County, Texas, connecting at Tap 138kV 8798 La Grulla - 8355 Goodwin. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/25/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0443
- Capacity
- 171 MW
- Fuel
- Solar (PV)
- Substation
- Tap 138kV 8798 La Grulla - 8355 Goodwin
- County
- Hidalgo County
- Interconnecting entity
- Sullivan Solar LLC
- Projected COD
- 02/25/2029
- Entered queue
- 03/22/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/06/2024Screening → FIS Requested
- 03/22/2024Entered the queue with 171 MW, projected COD 02/25/2029