26INR0440 · Solar · Jones County
Hamby Solar
Hamby Solar is a 206 MW solar project in Jones County, Texas, connecting at 6245 ABILENE ROBERTSON PRISON 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/27/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0440
- Capacity
- 206 MW
- Fuel
- Solar (PV)
- Substation
- 6245 ABILENE ROBERTSON PRISON 138 KV
- County
- Jones County
- Interconnecting entity
- Abilene GCE LLC
- Projected COD
- 06/27/2028
- Entered queue
- 03/20/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/31/2025FIS Requested → IA Signed
- 03/20/2024Entered the queue with 206 MW, projected COD 06/27/2028
- 03/20/2024Screening → FIS Requested