26INR0427 · BESS · Austin County

BremRaek BESS

BremRaek BESS is a 201 MW battery storage project in Austin County, Texas, connecting at 7271 LCRA New Bremen 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/14/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0427
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
BremRaek BESS
Projected COD
11/14/2027
Entered queue
02/28/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/28/2024
    Entered the queue with 201 MW, projected COD 11/14/2027
  • 02/28/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.