26INR0402 · BESS · Hill County

HILLBORO BESS

HILLBORO BESS is a 131 MW battery storage project in Hill County, Texas, connecting at Tap 138kV Ash Creek Switch (Bus #3473) – Revolution Switch (Bus #3387). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/21/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0402
Capacity
131 MW
Fuel
BESS (BA)
Interconnecting entity
Abei Energy Green XI LLC
Projected COD
09/21/2028
Entered queue
02/27/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/14/2024
    Screening → FIS Requested
  • 02/27/2024
    Entered the queue with 131 MW, projected COD 09/21/2028

Other projects at this substation

HILLBORO WINDWind33 MWFIS Requested