26INR0362 · BESS · Matagorda County
Midfield BESS Project SLF
Midfield BESS Project SLF is a 0 MW battery storage project in Matagorda County, Texas, connecting at Tap 138kV 8121 Blessing - 8125 Lolita. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0362
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV 8121 Blessing - 8125 Lolita
- County
- Matagorda County
- Interconnecting entity
- HQC Solar Holdings 1, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 05/07/2024
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/07/2024Entered the queue with 0 MW, projected COD 07/01/2028
- 05/07/2024Screening → FIS Requested
Other projects at this substation
| Midfield PV Project SLF | Solar | 150 MW | FIS Requested |