LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0355 · BESS · Glasscock County

Pleiades Storage

Pleiades Storage is a 206 MW battery storage project in Glasscock County, Texas, connecting at Tap 138kV Einstein 23852 - 10043 St. Lawrence. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 09/22/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0355
Capacity
206 MW
Fuel
BESS (BA)
Interconnecting entity
Pleiades Storage, LLC
Projected COD
09/22/2029
Entered queue
02/23/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/17/2025
    FIS Requested → FIS Approved
  • 02/23/2024
    Entered the queue with 206 MW, projected COD 09/22/2029
  • 02/23/2024
    Screening → FIS Requested

Other projects at this substation