26INR0340 · BESS · Galveston County
SOUTHERN SELECT ENERGY STORAGE
SOUTHERN SELECT ENERGY STORAGE is a 205 MW battery storage project in Galveston County, Texas, connecting at Bus Name: TNHEIGHTS_1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/24/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0340
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- Substation
- Bus Name: TNHEIGHTS_1
- County
- Galveston County
- Interconnecting entity
- SOUTHERN SELECT ENERGY STORAGE LLC
- Projected COD
- 05/24/2027
- Entered queue
- 10/12/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/20/2026FIS Requested → FIS Approved
- 05/09/2025FIS Approved → IA Signed
- 10/12/2023Entered the queue with 205 MW, projected COD 05/24/2027
- 10/12/2023Screening → FIS Requested