26INR0333 · BESS · Galveston County

VERTUS ENERGY STORAGE

Withdrawn

VERTUS ENERGY STORAGE is a 207 MW battery storage project in Galveston County, Texas, connecting at Bus Name: TnMainland1,. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0333
Capacity
207 MW
Fuel
BESS (BA)
Interconnecting entity
VERTUS ENERGY STORAGE LLC
Projected COD
07/06/2026
Entered queue
10/10/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Listed as withdrawn UNCONFIRMED
  • 01/30/2026
    Energization Approved → Sync Approved
  • 12/16/2025
    IA Signed → Energization Approved
  • 01/08/2025
    FIS Approved → IA Signed
  • 09/09/2024
    FIS Requested → FIS Approved
  • 10/10/2023
    Entered the queue with 207 MW, projected COD 07/06/2026
  • 10/10/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.