26INR0333 · BESS · Galveston County
VERTUS ENERGY STORAGE
Withdrawn
VERTUS ENERGY STORAGE is a 207 MW battery storage project in Galveston County, Texas, connecting at Bus Name: TnMainland1,. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0333
- Capacity
- 207 MW
- Fuel
- BESS (BA)
- Substation
- Bus Name: TnMainland1,
- County
- Galveston County
- Interconnecting entity
- VERTUS ENERGY STORAGE LLC
- Projected COD
- 07/06/2026
- Entered queue
- 10/10/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Listed as withdrawn UNCONFIRMED
- 01/30/2026Energization Approved → Sync Approved
- 12/16/2025IA Signed → Energization Approved
- 01/08/2025FIS Approved → IA Signed
- 09/09/2024FIS Requested → FIS Approved
- 10/10/2023Entered the queue with 207 MW, projected COD 07/06/2026
- 10/10/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.