LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0319 · BESS · Wise County

Sandford Storage

Sandford Storage is a 101 MW battery storage project in Wise County, Texas, connecting at Tap 345kV Bird Dog (Bus #11736) - Jacksboro (Bus #1429). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0319
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
BT Sandford Solar, LLC
Projected COD
01/30/2029
Entered queue
12/12/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/12/2023
    Entered the queue with 101 MW, projected COD 01/30/2029
  • 12/12/2023
    Screening → FIS Requested

Other projects at this substation

Sandford SolarSolar126 MWFIS Requested