26INR0310 · BESS · Haskell County
Quantum Storage
Quantum Storage is a 322 MW battery storage project in Haskell County, Texas, connecting at 60089 Kilby Switching Station 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/01/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0310
- Capacity
- 322 MW
- Fuel
- BESS (BA)
- Substation
- 60089 Kilby Switching Station 345kV
- County
- Haskell County
- Interconnecting entity
- IP Quantum II BESS, LLC
- Projected COD
- 09/01/2026
- Entered queue
- 10/26/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/10/2026Energization Approved → Sync Approved
- 03/26/2026IA Signed → Energization Approved
- 06/16/2025FIS Requested → FIS Approved
- 02/22/2024Screening → FIS Requested
- 10/26/2023Entered the queue with 322 MW, projected COD 09/01/2026
- 10/26/2023FIS Approved → IA Signed