26INR0296 · BESS · Pecos County
Sherbino II BESS SLF
Sherbino II BESS SLF is a 77 MW battery storage project in Pecos County, Texas, connecting at 38430 TNMP White baker Switching Station 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/19/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0296
- Capacity
- 77 MW
- Fuel
- BESS (BA)
- County
- Pecos County
- Interconnecting entity
- Phoenix Battery Storage, LLC
- Projected COD
- 04/19/2027
- Entered queue
- 11/16/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/23/2025FIS Requested → FIS Approved
- 08/01/2024FIS Approved → IA Signed
- 11/16/2023Entered the queue with 77 MW, projected COD 04/19/2027
- 11/16/2023Screening → FIS Requested