26INR0291 · BESS · Schleicher County
Cold Creek Storage 2
Cold Creek Storage 2 is a 172 MW battery storage project in Schleicher County, Texas, connecting at Tap 345kV line Big Hill (#76003) - Twin Buttes (#76009). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/28/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0291
- Capacity
- 172 MW
- Fuel
- BESS (BA)
- County
- Schleicher County
- Interconnecting entity
- Cold Creek Solar and Storage LLC
- Projected COD
- 05/28/2028
- Entered queue
- 11/02/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/23/2025FIS Requested → IA Signed
- 11/02/2023Entered the queue with 172 MW, projected COD 05/28/2028
- 11/02/2023Screening → FIS Requested
Other projects at this substation
| Cold Creek Solar 2 | Solar | 432 MW | IA Signed |