ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0280 · BESS · Wichita County

Pethrus BESS

Pethrus BESS is a 174 MW battery storage project in Wichita County, Texas, connecting at Tap Wichita Falls Switch (#1464) – North Star (#1467) 138 kV Line. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/03/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0280
Capacity
174 MW
Fuel
BESS (BA)
Interconnecting entity
Pethrus BESS, LLC
Projected COD
03/03/2029
Entered queue
08/30/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/18/2025
    FIS Requested → FIS Approved
  • 08/30/2023
    Entered the queue with 174 MW, projected COD 03/03/2029
  • 08/30/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.