26INR0256 · Solar · Houston County
Camino Ranch Solar 2 SLF
Camino Ranch Solar 2 SLF is a 237 MW solar project in Houston County, Texas, connecting at Tap to Jim English (#3351) – Flat Branch (#3345) 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/09/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0256
- Capacity
- 237 MW
- Fuel
- Solar (PV)
- County
- Houston County
- Interconnecting entity
- Camino Ranch Solar Project LLC
- Projected COD
- 12/09/2028
- Entered queue
- 01/10/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/08/2026FIS Requested → FIS Approved
- 12/31/2025FIS Approved → IA Signed
- 01/10/2024Entered the queue with 237 MW, projected COD 12/09/2028
- 01/10/2024Screening → FIS Requested
Other projects at this substation
| Camino Ranch Solar SLF | Solar | 296 MW | IA Signed |
| Camino Ranch Storage SLF | BESS | 298 MW | IA Signed |
| Camino Ranch Storage 2 SLF | BESS | 238 MW | IA Signed |