26INR0196 · Solar · Duval County

Realitos Solar SLF

Withdrawn

Realitos Solar SLF is a 150 MW solar project in Duval County, Texas, connecting at Bruni (#8297) – Crestonio (#8695) 138 kV line; AEP. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0196
Capacity
150 MW
Fuel
Solar (PV)
Interconnecting entity
Mesquite Creek LLC
Projected COD
12/15/2028
Entered queue
07/20/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/24/2026
    Listed as inactive
  • 07/20/2023
    Entered the queue with 150 MW, projected COD 12/15/2028
  • 07/20/2023
    Screening → FIS Requested

Other projects at this substation

Realitos Storage SLFBESS0 MWWithdrawn