LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0177 · BESS · Houston County

Dionysus Storage

COD delayed 1×

Dionysus Storage is a 77 MW battery storage project in Houston County, Texas, connecting at Tap 138kV 6733 Mustang Prairie - 6732 Latexo. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0177
Capacity
77 MW
Fuel
BESS (BA)
Interconnecting entity
Dionysus Solar, LLC
Projected COD
12/15/2028
Entered queue
06/05/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 03/11/2027 → 12/15/2028 (+21 months)
  • 07/31/2026
    FIS Requested → IA Signed
  • 06/05/2023
    Entered the queue with 77 MW, projected COD 03/11/2027
  • 06/05/2023
    Screening → FIS Requested

Other projects at this substation

Dionysus SolarSolar153 MWIA Signed