ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0172 · Solar · Hardeman County

Lazy U Solar 2

Lazy U Solar 2 is a 252 MW solar project in Hardeman County, Texas, connecting at Tap 345kV 60505 EDITHCLA7B - 60501 TESLA7A ckt2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0172
Capacity
252 MW
Fuel
Solar (PV)
Interconnecting entity
Lazy U Solar 2
Projected COD
06/30/2029
Entered queue
08/15/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/15/2023
    Entered the queue with 252 MW, projected COD 06/30/2029
  • 08/15/2023
    Screening → FIS Requested

Other projects at this substation

Lazy U Solar 1Solar252 MWFIS Requested