26INR0159 · BESS · Schleicher County

Proving Ground BESS

Proving Ground BESS is a 51 MW battery storage project in Schleicher County, Texas, connecting at Tap 138kV 6500 Live Oak - 6490 Santiago. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0159
Capacity
51 MW
Fuel
BESS (BA)
Interconnecting entity
Lantana Solar LLC
Projected COD
06/30/2028
Entered queue
07/10/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/26/2024
    Screening → FIS Requested
  • 07/10/2023
    Entered the queue with 51 MW, projected COD 06/30/2028

Other projects at this substation

No other projects at this substation.