26INR0147 · Solar · Lampasas County
Seven Springs Solar
Seven Springs Solar is a 145 MW solar project in Lampasas County, Texas, connecting at Tap 7061 COPPERAS COVE 7260 Kempner 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/26/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0147
- Capacity
- 145 MW
- Fuel
- Solar (PV)
- County
- Lampasas County
- Interconnecting entity
- Hancock Springs, LLC
- Projected COD
- 05/26/2028
- Entered queue
- 09/05/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/28/2025FIS Requested → IA Signed
- 09/05/2023Entered the queue with 145 MW, projected COD 05/26/2028
- 09/05/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.