LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0143 · Solar · Kleberg County

Santa Garcias Solar

Santa Garcias Solar is a 265 MW solar project in Kleberg County, Texas, connecting at Tap 138kV 8515 Alazan - 8458 Barney Davis. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/30/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0143
Capacity
265 MW
Fuel
Solar (PV)
Interconnecting entity
Oxy Renewable Energy LLC
Projected COD
05/30/2029
Entered queue
06/07/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/31/2025
    FIS Requested → IA Signed
  • 06/07/2023
    Entered the queue with 265 MW, projected COD 05/30/2029
  • 06/07/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.