26INR0134 · Solar · Bee County
Myers Solar
Myers Solar is a 102 MW solar project in Bee County, Texas, connecting at 8629 Baez 69 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/22/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0134
- Capacity
- 102 MW
- Fuel
- Solar (PV)
- Substation
- 8629 Baez 69 kV
- County
- Bee County
- Interconnecting entity
- BT Myers Solar, LLC
- Projected COD
- 05/22/2028
- Entered queue
- 06/01/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/01/2023Entered the queue with 102 MW, projected COD 05/22/2028
- 06/01/2023Screening → FIS Requested
Other projects at this substation
| Myers Storage | BESS | 76 MW | FIS Requested |